The road construction took last Sat, Sun and Mon off. They started a new section of road a few hundred feet from the Capricorn turnoff on Tuesday. As of yesterday (Thursday) evening about 600ft of one side of this new section had been poured, equivalent to 300 feet of full road.
So, it appears that the road is going in at approx. 100ft per day. There's about 11,400 feet to go. That's 114 days assuming no more days off are taken due to holidays, bad weather etc. If we add another 30 days, because days off for those reasons are inevitable, it means the road will be completed in about 150 days, ie. near the end of February.
Speed bumps: I think there will be an initiative from the Town Board to install properly engineered concrete speed bumps and interested parties will be able to "buy" sections of each speed bump. If this goes ahead the speed bumps will be pre-cast in sections, maybe 4 per bump, and installed over time. I am sure this will be of particular interest to resorts, residential parties etc.